# What is FAT and SAT and how are they different

**URL:** <https://forumautomation.com/t/what-is-fat-and-sat-and-how-are-they-different/9266>\
**Category:** Field Instrumentation\
**Created:** [March 20, 2021, 10:15am UTC](https://forumautomation.com/t/what-is-fat-and-sat-and-how-are-they-different/9266 "2021-03-20T10:15:45Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![instrumentationtechi](https://forumautomation.com/letter_avatar_proxy/v4/letter/i/50afbb/32.png) [@instrumentationtechi](https://forumautomation.com/u/instrumentationtechi)\
**Post date:** [March 20, 2021, 10:15am UTC](https://forumautomation.com/t/what-is-fat-and-sat-and-how-are-they-different/9266/1 "2021-03-20T10:15:45Z")

</div>

Explain the factory acceptance test and site acceptance test

---

<div class="post-metadata">

**Author:** ![ashlin](https://forumautomation.com/user_avatar/forumautomation.com/ashlin/32/3775_2.png) [@ashlin](https://forumautomation.com/u/ashlin)\
**Post date:** [March 20, 2021, 10:18am UTC](https://forumautomation.com/t/what-is-fat-and-sat-and-how-are-they-different/9266/2 "2021-03-20T10:18:13Z")

</div>

Factory Acceptance Tests (FAT) are the set of tests to be performed at the supplier’s site, i.e. the factory. Site Acceptance Testing (SAT) is the set of tests to be performed at the customer’s site, i.e. the new location of the equipment.