# Instrument Earth pit

**URL:** <https://forumautomation.com/t/instrument-earth-pit/249>\
**Category:** Field Instrumentation\
**Created:** [February 19, 2015, 9:39am UTC](https://forumautomation.com/t/instrument-earth-pit/249 "2015-02-19T09:39:11Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![gajoshi17](https://forumautomation.com/letter_avatar_proxy/v4/letter/g/e36b37/32.png) [@gajoshi17](https://forumautomation.com/u/gajoshi17)\
**Post date:** [February 19, 2015, 9:39am UTC](https://forumautomation.com/t/instrument-earth-pit/249/1 "2015-02-19T09:39:19Z")

</div>

Hi,

I am working on a fuel farm automation project of Airport. We have supplied DCS system. I came to know after visiting site that there is no separate earth pits are available for instrument system. All the earthing system including lightning are connected to a single grid. I am using IS, Non IS and FF devices and have separate busbars for each in the DCS panel. Since a common grid is there, I am getting continuity between all. Now the construction work at site is already completed. Is there any way I can make sure safety of my system and instruments and provide isolation??

Thanks in advance GJ

---

<div class="post-metadata">

**Author:** ![fadhil](https://forumautomation.com/letter_avatar_proxy/v4/letter/f/b19c9b/32.png) [@fadhil](https://forumautomation.com/u/fadhil)\
**Post date:** [March 15, 2015, 5:54pm UTC](https://forumautomation.com/t/instrument-earth-pit/249/2 "2015-03-15T17:54:46Z")

</div>

Generally you need to have system earth and electrical earth separate. Raise it as concern and make minutes of meeting and circulate to project team. But make sure at the end they dont ask you to build one for free!