# Difference Between FAT and SAT

**URL:** <https://forumautomation.com/t/difference-between-fat-and-sat/13165>\
**Category:** Field Instrumentation\
**Tags:** interviewquestions\
**Created:** [April 16, 2025, 12:49pm UTC](https://forumautomation.com/t/difference-between-fat-and-sat/13165 "2025-04-16T12:49:11Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![Rabert](https://forumautomation.com/user_avatar/forumautomation.com/rabert/32/6784_2.png) [@Rabert](https://forumautomation.com/u/Rabert)\
**Post date:** [April 16, 2025, 12:49pm UTC](https://forumautomation.com/t/difference-between-fat-and-sat/13165/1 "2025-04-16T12:49:11Z")

</div>

> # Difference Between FAT and SAT

FAT and SAT are two types of testing that are frequently utilized in industrial, manufacturing, & engineering projects, notably for equipment & control systems.

 ![image](https://cdn.forumautomation.com/original/2X/2/2a1f6b63d52f51a05c727ade2b145fa4fe1e50b5.jpeg)

> # Factory Acceptance Test (FAT)

Testing is performed at the manufacturer’s (or) supplier’s facility before the equipment is supplied to the client.

**Purpose:**

Prior to delivery, ensure that the equipment/system meets design standards and performs properly. Catch faults early to save costly on-site repairs.

**Includes:**

- Functionality tests.
- Control system logic verification
- Simulated inputs and outputs.
- Documentation review

**Performed By:**

Vendor/manufacturer, with (or) without the consumer present.

> # Site Acceptance Test (SAT)

Testing is performed at the final installation site, once the system has been delivered & installed.

**Purpose:**

Ensure system functionality in real-world operations. Confirm the integration with other systems.

**Includes:**

- Re-testing of functions examined during FAT.
- Power-up and I/O checks.
- Integration with external systems.
- Environmental performance (temperature, humidity, network)

**Performed By:**

Customer or end-user, typically with vendor assistance.

If you’re managing a project that includes both, the typical approach is:

> ### FAT Shipment→Installation→SAT →Commissioning